Ground Improvement

Soft Foundation Treatment Project of Yishang Dushan Port Intelligent Equipment Manufacturing and E-commerce Logistics Industrial Park Project

Release time:Apr 20,2023
Number of views:
Share:
Soft Foundation Treatment Project of Yishang Dushan Port Intelligent Equipment Manufacturing and E-commerce Logistics Industrial Park Project


易商独山港智能装备制造和电商物流产业园项目
 
Yishang Dushan Port Intelligent Equipment Manufacturing and E-commerce Logistics Industrial Park Project
Project Name: Yishang Dushan Port Intelligent Equipment Manufacturing and E-commerce Logistics Industrial Park Project
Construction content: To solve the problem of post construction settlement of muddy soil layers, plastic drainage boards combined with vacuum preloading drainage consolidation method are used to reinforce the soft foundation of the site
Project scale: This project covers an area of 100000.9 square meters, with an area of 100000.9 square meters
detailed information
The site of the Yishang Dushan Port Intelligent Equipment Manufacturing and E-commerce Logistics Industrial Park project is located in Dushan Port Town, Pinghu City, Jiaxing City. The south side is Haihe Road, the west side is Planned Binhai Road, and both the north and east sides are open spaces. Please refer to the overall plan of soft foundation treatment for details. This project covers an area of 100000.9 square meters and plans to build four four story ramp warehouses and related ancillary facilities. The project covers an area of 100000.9 square meters.
Design scheme for soft foundation treatment
After the design and demonstration by the Shengzhou team, a soft foundation treatment plan has been determined, and the project needs to solve the problem of post construction settlement of the muddy soil layer; The bearing capacity of foundation soil. The overall plan adopts plastic drainage boards combined with vacuum preloading drainage consolidation method to treat the soft foundation of the site; Among them, the vacuum preloading method adopts the "non drainage sand cushion vacuum preloading method" (Shengzhou invention patent), which has low cost, short construction period, and environmental protection and low consumption.
 
易商独山港智能装备制造和电商物流产业园项目


Construction content
Vertical drainage channel - construction of plastic drainage boards
Horizontal drainage system construction - laying pipelines (installing corrugated pipes and plate pipe connectors)
Sealing wall
Filling cofferdam
The project started construction on October 18, 2019, and Zone A entered dead load with vacuum preloading on January 15, 2020. Zone B is expected to enter dead load with vacuum preloading on April 10, 2020. It will be completed and delivered for acceptance on July 15, 2020, and the overall duration is expected to be 272 days